In brief
Check importer eligibility, the trusted operator, import VAT authorization and the thirty-day procedures for goods leaving suspension.
A Saudi importer plans regular releases from a bonded zone to the local market. Before finance schedules one later customs declaration for those movements, it needs to establish that the importer, operator and goods qualify for the subsequent-declaration procedure.
ZATCA’s consolidated Rules Regulating Customs Procedures, Article 39(6), sets the conditions. The Bonded Zones Procedure Guide, Chapter II section 6, then explains the approved forms and importer approval. Read both when setting up the release process.
Establish the importer’s eligibility before the first movement
Article 39(6) requires the paragraph 1 conditions, membership of the economic operator programme, customs procedures completed through a trusted operator and ZATCA authorization for the importer to pay import VAT through its VAT return. Excise goods are excluded from this subsequent-declaration route.
The paragraph 1 file should establish imports recorded under the commercial registration, Saudi residence, at least twelve months of VAT registration, filing and payment compliance, the specified absence of proven Zakat, tax or customs evasion in the preceding three years, the liquidation condition and financial solvency under Annex 2. Record the approvals and conditions applicable to the actual importer and operator.
Assign the forms and the declaration to their owners
The November 2026 procedure guide describes an approved exit form of the subsequent-declaration type submitted by the operator or its delegate. The importer or representative authorizes preparation of the customs declaration form by the zone operator or delegate. The importer then approves the customs declaration.
| Control record | What finance and logistics should reconcile |
|---|---|
| Importer approval file | Importer identity, programme membership and authorization to account for import VAT through the return |
| Operator arrangement | The trusted operator completing the customs process, with the actual delegation |
| Each physical exit | Approved form reference, movement date, product, quantity and destination |
| Subsequent declaration | The exit records included, accepted values, duties and importer approval |
| VAT close | The import amounts under the effective return-payment authorization and the separately supported deduction |
Article 39(6) requires the subsequent customs declaration within thirty days and approved forms during the periodic operations. The guide separately refers to submitting the approved exit form within a period not exceeding thirty days, followed by importer approval of the declaration. Confirm the applicable platform period and approved procedure when setting the calendar. Record the start event and deadline in the operating file so the team can demonstrate how it calculated them.
Reconcile the goods before closing the declaration
Dariba illustration. An approved importer releases 25, 35 and 20 units from suspended stock under three approved exit records. The declaration schedule should reconcile 80 units across three exit records. Assume an accepted customs value of SAR 1,000 per unit throughout. The schedule starts with SAR 80,000 of customs value, then reconciles the applicable assessment and return-payment entries using the actual classification, rate and charges.
If an additional ten units remain in the zone, keep them in the remaining suspended stock. If the warehouse reports 85 units departed, investigate the five-unit difference and establish the correct customs records before closing the movement schedule.
Keep the procedure approval and subsequent declaration with the movement evidence. Our bonded-zone entry and exit guide follows the inventory through each destination.
Complete the import VAT review
Use the effective Article 44 authorization for VAT payment through the return. Review input deduction under Article 49 against the importer’s evidence and use of the goods. Tie the customs declaration and its import values to the VAT workpaper, including amendments, so each amount is included in the appropriate period. The import relief and deferral guide covers the VAT conditions.
Sources
- ZATCA Rules Regulating Customs Procedures, consolidated Arabic textDecision 28624 with amendments through Decision 13-99-1448. Exact articles and printed pages are identified in the text.
- ZATCA Bonded Zones Procedure Guide, first edition November 2026Chapter II section 6 and Chapter III section 1. Approved exit forms, importer authorization, subsequent declarations and transit completion.
- Saudi VAT Implementing Regulations, current Arabic textArticles 43–44 and 49. Import payment and deduction follow their actual conditions.