In brief
Additional development time is conditional: support the invoice and licence, maintain progress, and model the collection consequences of failure or early sale.
An approved additional development period can give a landowner more time to finish the required work and affect collection. It is not a declaration that the land has stopped being subject to white-land fees. The Ministry’s technical controls expressly preserve annual invoicing and specify what happens if the project is not completed or the land is sold before completion.
This guide analyses White-Land Regulations Article 8(3), the related payment/refund provisions and the published Technical Controls for Determining the Additional Period for Development of Land Subject to the White Land and Vacant Property Fees Law. The controls concern the white-land development route; they are not a general vacancy extension for an unused building.
Identify the invoice, project route and requested period
The controls define the additional period as time after the fee’s due period for completing development or construction. Their scope includes infrastructure, infrastructure with superstructure, the specified updated planning routes, building on developed land, and the relevant off-plan or real-estate-contribution licences.
Start with the particular invoice to be extended. An owner cannot assume that a general master-plan discussion has extended every invoice for every parcel. Under General Provisions paragraph 4, the granted period is notified after approval and calculated from the end of the extended invoice’s relevant period; it is not simply added to the application date.
References: Technical Controls, First–Second and Fifth(4); Regulations Article 8(3).
Meet all application and document conditions
Third requires the application for the particular invoice and a current qualifying approval/licence: the specified raw-land plan approval, building permit, comprehensive-development licence, final approval under the updated routes, off-plan sale licence or real-estate-contribution licence. The document’s date must correspond to the invoice year or precede it.
Where more than six months is requested, provide a schedule from an accredited engineering office showing the time needed to finish, subject to the stated exception for off-plan and real-estate-contribution projects. A budget or non-binding contractor estimate is not automatically that prescribed document.
Dariba recommendation: reconcile the title, invoice year, licence route, licence validity and schedule before submission. Seek a decision early enough to manage the existing payment obligation; no unsupported universal application cutoff is invented here.
Reference: Technical Controls, Third(1)–(3).
Longer periods trigger additional review
The committee estimates the necessary time from area, topography, floors, built areas and project schedule. If the additional period exceeds four years, Fourth(2) requires the further engineering-office report and specified Balady classification/certification conditions, including the relevant service categories and first- or second-grade classification.
For requests exceeding three years, the committee refers the documents and schedules to Etmam to assess their realism and feasibility and recommend before determination. Three years and four years trigger different requirements; they should not be collapsed into one threshold.
The committee may request further data or studies. Etmam’s indicative development-period schedule requires the prescribed committee agreement and ministerial approval. An indicative project duration is not an owner’s automatic entitlement to that period.
Reference: Technical Controls, Fourth(1)–(5).
Distinguish co-owner treatment from later invoices
After accepting a request, the committee may grant a similar period to the other liable persons for the same land where they satisfy the conditions. This is not automatic relief for every co-owner or a separate parcel held by an associated company.
Fourth(7) separately provides that invoices issued during the additional period are automatically extended to end with the extended invoice. General Provisions paragraph 1 nevertheless says that the fee continues to be issued annually, with the objection right preserved.
The consequence is a distinction between annual assessment/invoicing and the approved collection timetable. A finance model that deletes all later annual charges merely because the first invoice was extended misses that distinction.
References: Technical Controls, Fourth(6)–(7) and Fifth(1).
Maintain progress reports and address cancellation risks
Fourth(8) requires the supervising engineering office’s progress report every six months. The committee can cancel the additional period for the specified reporting failure within the stated sixty-day requirement. Preserve the actual due and submission dates rather than assume that reports are only needed at final completion.
Fourth(9) also permits cancellation where lack of seriousness/default is established and progress deviates by more than 15%. The committee may allow a single corrective period of no more than 180 days. That discretion is not an automatic additional six months on every delayed project, and the provision should not be recast as an invented percentage-point calculation.
For an extension based on an off-plan or real-estate-contribution licence, Fourth(10) permits reliance on reports from the competent authority under the relevant legislation. The committee determines the additional period under its approved work rules in paragraph 11.
Reference: Technical Controls, Fourth(8)–(11).
Understand completion, failure and sale before signing a transaction
General Provisions paragraphs 2 and 5 provide collection consequences after expiry or cancellation if development/construction is not completed, including fees for the statutory and additional periods. Additional time should therefore be modelled as conditional treatment with potential accumulated liability.
Paragraph 3 states that where the owner wishes to sell during the additional period before completion, the period ends and the land fees must be paid before ownership transfer. A sale is not automatically a way of exporting the extension’s unpaid liability to the buyer.
Regulations Article 13(4) separately provides repayment where the required development/construction is completed within the statutory or granted additional period and the fee has already been paid. Maintain evidence of actual compliant completion; beginning works, fencing or a progress percentage does not by itself satisfy completion.
Dariba original illustration: assume two annual invoices of SAR 100,000 each remain within an approved additional period. A model showing zero merely because collection is deferred can conceal SAR 200,000 of invoiced exposure if failure-to-complete conditions result in collection. This assumes the invoices and amounts are valid and does not establish a particular owner’s final liability or refund.
References: Technical Controls, Fifth(2)–(5); Regulations Articles 1, 8(3) and 13(3)–(4).
Keep approval, evidence and dispute rights in one file
The controls are issued under the prescribed ministerial/committee process and apply from their publication under Fifth(6)–(7). Use the actual published instrument and the owner’s approval, not a promotional statement that “developers can get more time”.
The practical file should connect the relevant invoice and payment period, licence, approved duration, Etmam/engineering material where required, subsequent invoices, reports, corrective decisions and completion or transfer plan. Preserve objection dates separately; project correspondence is not itself an objection under Law Article 8.
The main white-land guide addresses liability, rate bands and invoices; the landowner FAQ explains common decisions. The analysis here is qualified application of the published provisions, not a Ministry approval or a guarantee that a requested extension will be granted.
Key takeaways
- Apply for the particular invoice with the qualifying licence or approval and required schedule.
- More than six months, three years and four years trigger different document/review requirements.
- Co-owner relief requires its conditions; later invoices have their specified extension treatment.
- Annual invoicing continues during the additional period.
- Six-month reports, the stated reporting deadline and progress deviation affect cancellation.
- A corrective period of up to 180 days is discretionary and available only under its conditions.
- Sale before completion ends the period and requires payment before transfer under the controls.
- Failure to complete can produce collection for statutory and additional periods.
Sources
- Vacant-Property Fees Implementing Regulations, published 15 May 2026Articles 1–18: distinct reference-year, city-decision, vacancy/count/utility, comparable-rent, stopping, notice and payment framework.
- Saudi White Land and Vacant Property Fees Law, amended by Royal Decree M/244 dated 7 Dhu al-Qidah 1446 AHArticles 1/3–8/13: scope, ceilings, ownership responsibility, objection and implementation. Ministry-published Arabic text incorporating the 2025 amendments.
- White-Land Fees Implementing Regulations, published 22 August 2025Articles 1–13: conditions, city/area/rate decisions, fifth-band aggregation, impediments, completion, payment and refund.
- Ministry Technical Controls for Additional White-Land Development PeriodsFirst–Fifth: invoice/licence requirements, six-month/three-year/four-year review distinctions, progress and cancellation, continued annual invoicing and sale/completion consequences.
- Ministry guide to objecting to a white-land fee invoicePortal steps and committee review. Practical service guidance does not extend the statutory filing period.
- Ministry key information on white-land feesOfficial rate-band and programme overview. Its ninety-day administrative review description is not a ninety-day objection-filing period or an amendment of the Law.
- Umm Al-Qura: adoption of the Vacant-Property Regulations, 15 May 2026Ministerial Decision 4700822503/1; publication/effect distinguished from specific geographical application.
- Umm Al-Qura: operative Vacant-Property RegulationsOfficial article text, checked against the Ministry-published attachment. Six-month wording, comparable-rent/value ceiling and notification-based payment periods retained.
General information only. Apply the controlling Arabic Law, regulations, technical controls and actual city/property decisions. Publication of a framework does not certify nationwide or individual liability. Official Ministry guidance and Dariba original illustrations are distinguished; procedural uncertainties and period conditions remain. No independent legal certification or Ministry approval is implied.