In brief
Screen contract values against the SAR 100,000 boundary and track the data, signing, amendment and cessation records required for disclosure.
A Saudi procurement team signs several private-sector contracts during a month. The tax workpaper should identify which contracts enter the disclosure file, the actual signing date and who will submit the required information.
Income Tax Law Article 61(c) and Implementing Regulations Article 58(2)(b) govern this reporting. The Regulations extend the obligation to the specified natural and legal persons, including persons outside ordinary CIT filing and the listed charitable, endowment and public bodies. Establish the reporting person and actual private-sector contract.
Screen each contract using its established value
The Regulations except contracts valued below SAR 100,000. A contract of exactly SAR 100,000 reaches the reportable boundary.
Dariba illustration. Assume the following are three separate procurement contracts within the provision’s scope, and their values have been correctly established for the statutory test.
| Contract | Established value | Screening outcome |
|---|---|---|
| A | SAR 99,999 | Below the stated boundary |
| B | SAR 100,000 | Included in the disclosure file |
| C | SAR 175,000 | Included in the disclosure file |
The workpaper records two reportable contracts with a combined value of SAR 275,000. Keep the signed documents and basis for the values with the screening. Review the actual arrangement where the documents, scope or value require interpretation.
Carry the required data into the disclosure
| Data | Evidence to retain |
|---|---|
| Parties and addresses | Correct legal names, capacity and contract details |
| Subject | Goods, services or work under the agreement |
| Value and financial terms | The established contract amount and payment terms |
| Implementation dates | Actual contractual performance timetable |
| Signing and disclosure | Executed agreement, signing date, filing and acknowledgement |
| Amendments | Executed amendment, changed data and disclosure record |
Article 58(2)(b) requires the basic contract information and amendments within a period not exceeding three months from signing, using its stated wording. Record the signing trigger and the actual amendments. Establish the applicable reporting procedure for a later amendment and preserve the underlying dates when seeking clarification.
Assign the submission to a named finance or tax owner and keep its acknowledgement linked to the contract. Record supplier registration and withholding analysis in the relevant schedules alongside the disclosure.
Open a separate cessation entry
The same provision requires notification of cessation for any reason and the rights arising for each party within thirty days from cessation. Obtain the actual cessation date and the resulting receivables, amounts payable or other contractual rights from the project or legal owner.
Dariba illustration. Contract C ends early. The closeout identifies a final SAR 12,000 payable to the contractor and a supported SAR 5,000 receivable for an advance balance. Record the two rights and their contractual basis with the cessation notification. Reconcile their eventual settlement through the ordinary ledger.
Keep the project closeout, notification and acknowledgement together. The original signing disclosure and the cessation entry each need their own evidence in the calendar.
Retain the file through review
The Regulations allow ZATCA to request a copy of the contract and state joint responsibility with the taxpayer for the resulting tax and penalties where the reporting obligation is breached. Establish the particular obligation and facts when reviewing a missing disclosure.
The CIT records and contract-disclosure guide explains the full framework, including information requests and records. The workpaper above is Dariba’s suggested way to connect procurement and closeout to those reporting duties.
Sources
- Saudi Income Tax Law, current Arabic textArticle 61(c) identifies the contract disclosure information and reporting obligation.
- Saudi Income Tax Implementing Regulations, current Arabic textArticle 58(2)(b), printed p.30, covers reportable contracts, the below-SAR-100,000 exception, signing, amendments and cessation.