Real Estate Transaction Tax

RETT on Long-Term Usufruct Rights Exceeding 50 Years in Saudi Arabia

Updated 21 November 20264 min read

Part of RETT in Saudi Arabia: The Complete Guide

In brief

A grant of real-estate usufruct for more than 50 years falls within RETT unless relief applies. Value the right under Regulations Article 2(f), distinguish the grant date from payment, and preserve the limitation in ZATCA's Example 10.

A long land-use right can produce a RETT liability even though the landowner keeps legal title. The first task is to identify the rights actually granted, their duration and any exemption. The contract’s label alone does not settle the result.

The duration test and its limits

Article 1 of the Zakat, Tax and Customs Authority’s Real Estate Transaction Tax Law includes transfers of ownership, permanent transfers of benefit, and transfers of benefit for more than 50 years, directly or indirectly. Regulations Article 2(f) supplies the valuation rule for a taxable grant exceeding that duration.

Exactly 50 years does not satisfy the more-than-50-year limb. A 45-year arrangement is not taxable under that limb solely because it is long. Neither statement proves that an arrangement containing a separate ownership transfer or permanent benefit is outside RETT.

Review extension rights and linked documents to establish the actual legal entitlement. The cited provisions do not create a universal rule that every optional renewal or consecutive lease must be added together. Law Article 6 and Regulations Article 6 concern fictitious or concealed arrangements; they are not a substitute for reading the rights granted. VAT treatment is a separate question, including the distinction between residential and commercial use.

Grant date, cancellation and payment

For cases where notarization has not occurred, Regulations Article 4(b) uses the date of granting the right, unless the grant is cancelled within 30 days. Article 5(b) then requires payment within 30 days of the relevant Article 4 date.

ZATCA’s Detailed RETT Guideline, Version 6, section 4.4, Example 11, printed page 20, illustrates disclosure and payment for a non-notarized agricultural usufruct exceeding 50 years. An agreement may itself grant the right; a later physical-access date is not automatically the tax date.

The cancellation wording matters, but it is narrow. Keep evidence that the grant was effectively cancelled within the stated period. Article 4(b) does not say that no aspect of the arrangement may have been performed. It also does not establish the result for every notarized transaction.

Cancellation after the window does not satisfy that particular exception. It does not make ordinary late-payment fines run from the grant date: Law Article 15(2) starts the ordinary fine on the day after the payment period ends. Any separate correction or refund ground must be tested on its own facts; see the RETT refund guide.

The valuation rule and the official example

Regulations Article 2(f) compares the present value of the right’s fair market value at the transaction date with the present value of the total agreed consideration, using the higher measure. The relevant asset is the right granted, rather than automatically the unrestricted freehold.

ZATCA Example 10: a 60-year usufruct with SAR 100,000 annual agreed consideration and SAR 200,000 annual market value; the guideline selects SAR 12 million without specifying a discount rate

ZATCA’s Example 10, printed page 18, uses a 60-year commercial usufruct, agreed annual consideration of SAR 100,000 and annual market value of SAR 200,000. It selects a SAR 12 million base. At 5%, the resulting tax is SAR 600,000; that multiplication is Dariba’s calculation.

There is an important limitation: SAR 12 million is also SAR 200,000 multiplied by 60. The example provides no discount rate, payment dates or discounted cash-flow schedule. It should not be presented as a demonstrated discounted valuation, or as an amendment removing the present-value wording from Article 2(f).

For an actual transaction, document the rights, term, premiums, payment timing and valuation assumptions. The cited provisions do not prescribe a universal discount rate. A supportable valuation and a request for ZATCA clarification can matter materially; an accredited valuation is evidence, rather than a guarantee that ZATCA must accept the declared amount. The Article 2(f) companion gives an expressly assumed cash-flow illustration.

Later price changes

Where the agreed consideration is amended after the transaction, Article 2(f) requires recalculation and a correction request if the tax increases or decreases, following Article 11. Keep the original and amended cash-flow schedules and explain the effect on both comparison measures.

A monitoring process should identify actual amendments. This is different from assuming that every forecast change or every scheduled review automatically creates a new agreed price. A reduction in the calculation does not itself transfer money back: the relevant correction and refund procedures still apply.

Exemptions and concession structures

A public-sector counterparty does not settle the exemption. A transfer to a qualifying public entity under Regulations Article 3(a)(4) is distinct from a transfer from a public entity acting as public authority under Article 3(a)(5). Test the actual direction, recipient and conditions rather than applying one public-sector label to the whole contract.

A concession can also contain a separate BOOT ownership transfer. Regulations Articles 2(g) and 4(c) govern that taxable transfer’s value and date; they do not defer every independent acquisition or usufruct grant inside the project. See the BOOT guide and the payment-deadline guide.

Keep one dated file linking the legal grant, valuation, exemption analysis, registration and payment. That makes the result reviewable throughout a contract that may last longer than the teams who negotiated it.

Key takeaways

  1. More than 50 years is the duration test; another ownership or permanent-benefit transfer needs its own analysis.
  2. For a non-notarized grant, Articles 4(b) and 5(b) identify the grant date and the 30-day payment period, subject to the stated cancellation exception.
  3. Article 2(f) compares two present-value measures. ZATCA's Example 10 does not demonstrate discounting or prescribe a discount rate.
  4. Cancellation after 30 days does not itself make payment late from the original grant date or eliminate every possible refund ground.
  5. An actual amendment to agreed consideration requires recalculation and a correction if tax increases or decreases.
  6. An exemption and any separate BOOT ownership transfer require their own conditions.

Frequently asked questions

Does a 45-year ground lease automatically escape all property taxes?

It does not meet the more-than-50-year duration limb by that term alone. Check whether the arrangement transfers ownership or a permanent benefit, what legal renewal rights exist, and the separate VAT rules. A short term does not establish a universal VAT classification or RETT exemption.

What happens if a 60-year grant is cancelled on day 20 or day 31?

For a non-notarized grant, Article 4(b) expressly excepts cancellation within 30 days. Cancellation on day 31 does not meet that exception. Payment timing and any separately available correction or refund must still be considered; late-payment fines start after the payment deadline, not automatically on the original grant date.

Does ZATCA's SAR 12 million example prove that annual rents must never be discounted?

No. Example 10 uses a 60-year term, SAR 200,000 annual market value and a SAR 12 million base, without a discount rate or cash-flow schedule. Article 2(f) still specifies present-value measures. Obtain a defensible valuation and clarification where the method materially affects tax.

Sources

Free toolRETT Exemption Checker

Reviewed against the RETT Law, the controlling Arabic Implementing Regulations and ZATCA's Detailed RETT Guideline Version 6 (May 2026). The guideline does not amend the legislation. Historical transactions need their applicable-period analysis. General information, not transaction-specific advice. Dariba.co is independent of ZATCA.